Renovation Update at SPORTIME Quogue
We are excited to share this update about our ongoing renovation and modernization project. We are working as quickly as possible to improve our facility and to enhance your experience at the club.
Here's what's happening:
- Our New Men's and Women's Locker Rooms will be open for member use starting Monday, December 16th! While there will be minor details still to be completed after this date, you can look forward to enjoying private showers and changing areas, beautiful new saunas, and many other upgraded amenities.
- Our New Group Exercise Studio is opening on Sunday, December 15th! This upgraded space will provide a more comfortable and intimate environment for your workouts, along with enhanced equipment and expanded programming. With the ongoing construction in our "stretch room" and in our existing group exercise room, we have shifted some equipment around on the second floor of our fitness center to allow space for stretching and more, until we are able to re-open the "stretch room".
- Indoor Tennis Courts: The exterior reconstruction of our tennis building is almost complete, and the refurbishing of the building's interior will begin later this month. As this process unfolds, there may be some temporary inconvenience to players, including temporary changes to the court lighting, but this will quickly lead to a new state-of-the-art LED lighting system and to a beautifully refinished tennis building. Crews will be working overnight to minimize disruptions to the schedule of play, and we will continue to keep as many courts open as possible during the renovation.
- Indoor Pickleball Courts: Now that the new group exercise studio is complete, we will begin the demolition of the current group exercise room, which will become an indoor pickleball center, featuring two state-of-the-art courts. We expect our pickleball courts to be open to members and players by the end of January and we cannot wait!
- Lobby Remodel: Starting in January, we will begin remodeling the lobby. At some points, the main entrance will need to be temporarily closed and traffic will be diverted to alternate entry points. We will, of course, try and minimize the interruption, and we will provide additional details and instructions closer to this phase of the project.
We will continue to share updates, and, of course, the club will remain open throughout the renovation period. If you have any questions, please feel free to reach out. We can't wait to share the new and improved SPORTIME Quogue with you!